Road Resurfacing in Whitpain – See This Week’s Schedule

Whitpain Township’s annual road resurfacing program got off to a strong start last week and work will continue in the coming days and will follow the schedule below( weather permitting):

Monday, August 13: North Wales Road

Tuesday, August 14: Finish North Wales Road and Yost Road

Wednesday, August 15: Jolly Road

Thursday, August 16: Cathcart Road

Friday, August 17: Makeup day in case of rain

As with any paving operation, this work is very weather dependent, and some streets listed on this year’s schedule may not be resurfaced until 2019 if Mother Nature doesn’t cooperate.